Project details
Description
BEAR Scotland has been commissioned by Transport Scotland to carry out resurfacing works on the A82 trunk road north of A82 Stoneymollan Roundabout (see Figure 1). The works will involve resurfacing and partial reconstruction of the A82 carriageway (northbound (NB) and southbound (SB)) carriageways. Surface and binder course will be replaced to varying depths, inlay will be replaced, and road markings/studs and kerbing will be reinstated following works. Minor/localised surface drainage amendments may also be undertaken as required.
The works are programmed for the 2024/25 Financial Year, currently programmed for March. Works will be undertaken during daytime programming (07:00 to 18:00), over 4 days. Changes in the programme may result in a change to the proposed working hours/commencement dates.
Site compounds are not required; access will be gained through Traffic Management (TM) on the carriageway. TM will entail lane closures during daytime hours, facilitated by a 10mph convoy and 4-way temporary traffic lights (TTLs). TM will be removed during the nighttime hours. Local access will be accommodated within the TM as far as is reasonably practicable.
Location
The scheme is located on the western periphery of Balloch in the West Dunbartonshire Local Authority (NGR: NS 38090 81469 - NS 38069 81586). Refer to Figure 1 (in PDF version) for map depicting the scheme location.