Annex A - BEAR Scotland slides
Slide 1
- A83 Taskforce
- Meeting Number 27
- Microsoft Teams
- 19 September 2024
- Eddie Ross
- NW Scheme Manager
Slide 2 - Presentation Overview
- Ongoing hillside monitoring regime
- A83 Rest and Be Thankful Landslide Event 15 September
- A83 Rest and Be Thankful – Debris Fence
- Communications
- Forestry and Land Scotland tree planting works
- Old Military Road
- A83 Aray Bridge
- Wider A83 / A82 works programme
Slide 3 - Hillside Monitoring Regime
Daily management of the route is continuing behind the scenes, to ensure it is safe for road users.
Daily:
- Remote weather station monitoring
- Expert wether forecasting
- Ground saturation estimates
- Remote timelapse photography
- Daily decision-making on use of A83 or OMR
- Additional site monitoring resources
2 weekly (depending on weather, more frequently):
- Site team observations on hillside condition and watercourse flows
- Hillside movement surveys and observations.
Slide 4 - A83 Rest and be Thankful Landslide - 15 September 2024
- Over-saturation of an area of hillside triggered a 500 Tonne landslide.
- Intercepted by debris fences and catchpits.
- A83 immediately closed as a safety precaution. Prompt mobilisation of the Old Military Road minimised the use of the long diversion route and ensured that Argyll and Bute remains open for business.
Slide 5 - A83 Rest and Be Thankful Landslide - 15 September 2024
- Immediate clean-up operations completed, regaining capacity in the debris pit.
- Traffic returned to A83 on Tuesday 17th September under convoy.
Slide 6 - A83 Rest and Be Thankful Landslide - 18 September 2024
- Continued movement and natural process, cleaning out of debris in the channel, continued after the event and was contained in the fences and pits.
- During the evening of 18 September the landslide source area extended bringing large boulders into the channel with concern of their potential to impact the A83.
- In darkness, traffic diverted onto the long diversion until the OMR was mobilised at daybreak with the safe removal of livestock.
- The continued saturation of the landslip source area in dry weather is being investigated to consider a solution.
- Traffic will remain on the OMR through into next week when heavy rain is forecast and reviewed thereafter.
Slide 7 - A83 Rest and Be Thankful - 3A/B Debris Fence
- Prep work underway for new debris fence above 3A / 3B Channel
- Drilling probe holes completed
- New access steps installed on slope
- Works will now be combined with long term solution ground investigation
Slide 8 - Communications
Use of OMR
- Emphasis moved to OPEN via OMR in releases and interviews
- Picked up by BBC,STV and local press
Landslide on 15 September
- Good use of images
Slide 9 - Old Military Road (Medium Term Solution)
- New link road commissioned and utilised
- Addresses previous flooding issues
- Adds resilience to the Old Military Road
Slide 10 - Forestry and Land Scotland – Tree planting works
- Phases 1 & 2 complete
- Phase 3 is ongoing
- Phase 4 to commence in 2025
Slide 11 - A83 Aray Bridge
- Works began on 6 September for approximately six weeks
- Works involve masonry repairs to the bridge parapet following damage caused by a vehicle collision, as well as final reinstatement of the stone pitching on the riverbed following storm damage on Oct 2023.
Slide 12 - Wider A83 / A82 (South) Programme
- Total A83 investment since May Taskforce ~ £2.68M
- £3M of further A83 investment planned for 2024/25 FY
- Total A82 (Tyndrum to Balloch) investment since January Taskforce ~ £270k
- £1.3M of further A82 investment planned for 2024/25 FY
Slide 13
- Thank You and Any Questions