Annex B - AtkinsRealis WSP Joint Venture Presentation

Slide 1

  • A83 Rest and Be Thankful​
  • Task Force No.27​
  • 19 September 2024​
  • Rory Gunn (AWJV)​

Slide 2 - LTS Design Development

Key Areas of progress:​

  • Fix A83 carriageway alignment and B828 Glen Mhor local road junction​
  • Refinement of the geotechnical aspects of the design, including further geohazard and rock-fall modelling​
  • Operational, fire and smoke assessments nearing conclusion​
  • Development of the debris flow shelter and protection wall ​
  • Construction methodology​
  • Consideration of the proposals for the Rest and Be Thankful Car Park and Viewpoint​
  • Environmental Impact Assessment being concluded​
  • Preparation of draft road Orders​
  • Remain on programme to publish draft Orders late 2024

Slide 3 - 2024 Look Ahead

Medium Term Solution:

Fences above A83

  • Conclude Debris / Rockfall modelling
  • Conclude performance specification
  • Initiate procurement exercise

Remainder of Phase 2/3

  • Design now fixed
  • Aim to publish EIAR and draft Orders end of 2024

Long Term Solution:

  • Conclude constructability assessment
  • Conclude Biodiversity Net Gain/ Natural Capital assessment work
  • Value for money review to refine cost estimates
  • Conclude Engineering, Environmental and Traffic & Economic Assessments
  • Continue Ground Investigation Fieldwork
  • Aim to publish EIAR and draft Orders end of 2024

Slide 4 - Statutory Process

Table showing Design Manual for Roads and Bridges (DMRB) Process and Typical Large Scale Infrastructure Project Timeline.

  • DMRB Stage 1 (Preliminary Engineering Study and Strategic Environmental Assessment - identification of broad improvement strategies) - Completed March 2021.
  • DMRB Stage 2 (Route option assessment and identification of preferred option) - Completed June 2023.
  • DMRB Stage 3(Development and assessment of preferred option) - Aim end of 2024.
  • Statutory Process (Publication of draft Road and Compulsory Purchase Orders and Environmental Impact Assessment Report; Public Local Inquiry (if required)) - 1 to 2 years (subject to statutory process and need for Public Local Inquiry).
    • Publications:
      • Draft Road Orders.
      • Draft Compulsory Purchase Order.
      • Environmental Impact Assessment Report.
    • Minimum 6 Week Statutory objection / representation period.
      • If no objections, progress completion of Statutory Process.
      • If objections:
        • Objection Resolution where possible.
        • If objections unresolved - Request Public Local Inquiry from Scottish Government.
      • Procurement – 1 year (subject to procurement route).

Slide 5 - Ground Investigations

Medium Term Solution Phases 2/3

  • Groundworks nearing completion in coming weeks

Long Term Solution

  • Tender awarded to Structural Soils Ltd
  • Groundworks commencing in coming weeks
  • 16 week groundwork period (subject to weather)
  • Majority of works on slopes above the A83
  • Some locations immediately below A83
  • This will require traffic management and single lane closures, likely over longer extents than currently experienced at present