Stakeholder Engagement

Overview

The STAG process is firmly founded on participation and consultation. Accordingly, public engagement has been pivotal to inform the A96 Corridor Review at all key stages. A comprehensive stakeholder engagement plan was developed at an early stage in the review process and has been carefully devised to ensure general inclusivity and representation of key equality groups.

Although there are no legal consultation requirements for EqIA, there has been engagement with the public throughout the Corridor Review in order to provide early opportunities within appropriate timeframes for opinions to be expressed on the transport intervention options for the A96 corridor as they have developed.

Public Consultation Activities

During the course of the A96 Corridor Review, there has been extensive public engagement. An initial four-week public consultation was held from 12 May 2022 to 10 June 2022. During this period, the public and stakeholders were invited to share insights into travel habits, general thoughts on travel and transport along the corridor and identify problems and potential opportunities along the route.

In total, 4,687 responses were received via the online consultation survey and email responses. A detailed overview of the findings are available in the Stakeholder and Public Engagement Consultation Report ( Transport Scotland (2022). A96 Corridor Review: Stakeholder & Public Engagement Consultation Report ) . A summary of the main findings are as follows:

  • 96% of respondents stated that car is their primary mode of travel on the A96 corridor
  • public transport is a less prevalent mode of transport with 46% of respondents indicating they do not use public transport along the route
  • 88% of respondents were very dissatisfied or dissatisfied with the availability of safe overtaking opportunities, 79% were very dissatisfied or dissatisfied with levels of traffic congestion and 76% were very dissatisfied or dissatisfied with the length of journey times
  • 37% were very dissatisfied or dissatisfied with the frequency of bus services, 43% were very dissatisfied or dissatisfied with the availability of safe walking infrastructure, 63% were very dissatisfied or dissatisfied with the cost of rail travel and 58% of respondents felt very unsafe or somewhat unsafe when using the road network.

The most frequently raised priority for the A96 Corridor Review, raised by 55% of respondents, was dualling the route, with only 12% of respondents opposed to full or partial dualling. Similarly, improving road safety was raised by 50% of respondents, which included general safety concerns as well as safety of driving, cycling and walking.

The need to improve rail services, including train connections, cost, and comfort of travel, was raised by 30% of respondents, and another 30% of respondents raised bypassing town centres. Other priorities listed by respondents include improvements to bus services (raised by 24% of respondents), general public transport improvements including public transport connectivity and integration (24% of respondents), and better road maintenance including infrastructure, surface, signage etc. (22% of respondents).

Section 1 of the consultation feedback form, ‘About You’, enabled diversity monitoring to be undertaken across a range of protected characteristics following data collection. The response rate varied across protected characteristic groups and many respondents either refused to answer or questioned the relevance of the questions. However, from the information that was provided, the following findings were identified:

  • The majority of children and young people felt somewhat unsafe or very unsafe when travelling along the A96 corridor (38%) compared to somewhat safe or very safe (26%).
  • A slightly higher proportion of female respondents travelled by car in the A96 corridor (66%) compared to male respondents (59%). However, a wider range of other transport modes were included in male respondents’ answers, including a number of work-related vehicles.
  • Very similar numbers of female (44.6%) and male (45.5%) respondents said they did not use public transport at all and reasons for this were similar. However, 12.5% of female respondents felt dissatisfied or very dissatisfied at bus stops and train stations, compared with only 7.9% of male respondents.
  • A higher proportion of those reporting no health conditions (47%) did not use public transport than those respondents who did report a disability or health condition lasting more than 12 months (41%).
  • Respondents who did report a disability or health condition lasting more than 12 months, were much more likely to be dissatisfied or very dissatisfied with accessibility on buses (16%) and trains (14%) than those who reported no condition (7%).

Stakeholder Engagement Activities

As part of the ongoing engagement with stakeholders, a series of stakeholder engagement sessions were held via an online collaboration platform to understand the views of different stakeholder groupings throughout the corridor. All sessions were attended by Jacobs AECOM representatives and split by the below stakeholder groupings:

  • representatives from the four local authorities and Highlands and Islands Transport Partnership (HITRANS)
  • environmental stakeholders, including local authority Environmental Planners
  • North East Scotland Transport Partnership (Nestrans) and Aberdeenshire Council
  • representatives from statutory environmental groups
  • representatives from active travel and accessibility stakeholders
  • representatives from business and business organisation stakeholders
  • representatives from Stagecoach
  • representatives from Police Scotland.

Across these sessions, consistent problems, opportunities and suggestions were provided on the topics outlined in Table 4-1.

Table 4‑1: Summary of Stakeholder Engagement Responses

Topic

Problems

Opportunities

Suggestions/ interventions

Active travel

Lack of appropriate active travel infrastructure, especially concerning safety while cycling and walking

Inclusivity and connectivity of active travel throughout the A96 corridor

Sustainable and safe active travel provision

Public transport

Low public transport uptake due to slow journey times, high travel costs and frequency of services

Reliable and sustainable public transport infrastructure improvements, including Demand Responsive Transport (DRT) and Community Transport (CT) links

Improvement to public transport services, including Park and Ride facilities, multi-modal transport hubs and interchanges between active travel and public transport

Road network

Lack of road safety and slow journey times

Sustainable travel and green infrastructure improvements to enhance connectivity

Sustainable road safety travel improvements with connectivity to public transport

Environment

Lack of green infrastructure and traffic emissions within towns along the route

Decarbonisation strategies, including electric vehicle charging infrastructure and sustainable travel infrastructure

Increase in green infrastructure

SEqIA Stakeholder Workshop

An online consultation workshop was held to present the SEqIA Scoping Report on 14 March 2023. Prior to this, the SEqIA Scoping Report was issued to 31 organisations (see Appendix B) representing equalities groups, socio-economically disadvantaged groups and islands communities, along with an invitation to attend the workshop.

Representatives from Jacobs AECOM were present and provided stakeholders with a comprehensive overview of the A96 Corridor Review process to date and the initial requirements of Transport Scotland in its duties to prepare an EqIA, CRWIA and FSDA.

The key feedback from these sessions included:

  • the need to consider the significant overlaps across the various social and equality impact topic areas and to consider intersectionality as part of the assessment
  • That where possible the assessments should refer to evidence provided by those with lived experience
  • the need to incorporate impacts on health into the assessments.

In addition, all attendees agreed they were content with scoping out an Islands and Communities Impact Assessment for the review.