Description of main environmental impacts and proposed mitigation

Air quality

Impacts

  • On site construction activities throughout Phases 1 and 2 carry the potential to produce airborne particulate matter, dust and generate emissions that may have a temporary impact on local air quality levels and act as a nuisance to nearby residents.
  • TM being implemented during both phases may result in an increase in associated vehicle emissions through idling vehicles and increased congestion.

Mitigation

Throughout both phases the following mitigation measures will be implemented:

  • Best practice and measures as outlined in the ‘Guidance on the assessment of dust from demolition and construction (January 2024)’ published by the Institute of Air Quality Management (IAQM), which includes the following mitigation relevant to this scheme will be followed:
  • The site layout will be planned (including plant, vehicles and Non-Road Mobile Machinery (NRMM)) so that machinery and dust causing activities are located away from receptors, as far as reasonably practicable;
  • Materials that have a potential to produce dust will be removed from site as soon as possible, unless being re-used on site (stockpiles will be covered or fenced to prevent wind whipping);
  • Cutting, grinding or sawing equipment will be fitted or used in conjunction with suitable dust suppression techniques such as water sprays or local extraction, e.g. suitable local exhaust ventilation systems;
  • Drop heights from conveyors and other loading or handling equipment will be minimised;
  • Vehicles carrying wastes and materials will be covered when entering and leaving the work area to prevent escape of materials during transport;
  • Equipment will be readily available on site to clean any dry spillages and spillages will be cleaned up as soon as reasonably practicable after the event using wet cleaning methods; and
  • When not in use, plant, vehicles and NRMMs will be switched off and there will be no idling vehicles.

Plant, vehicles and NRMM will be regularly maintained, paying attention to the integrity of exhaust systems to ensure such fuel operated equipment is not generating excessive fumes.

The following additional measure will be implemented:

  • Green driving techniques will be adopted, and effective route preparation and planning will be undertaken prior to works.
  • Where possible, materials will be sourced locally.
  • Surfaces will be swept where loose material remains following planing.

No significant effects are predicted on air quality. Therefore, in accordance with DMRB Guidance document LA 105: Air Quality no further assessment is required.

Landscape and visual effects

Impacts

  • There will be no operational impacts on visual receptors as both phases of work entail the like-for-like resurfacing of the A77 carriageway within the scheme extents.
  • Visual receptors identified (core path ID- SA63 & A77 carriageway users) have the potential to be visually impacted by the scheme during construction due to the presence of TM, plant, vehicles, machinery and operatives.
  • The general setting of the area along the A77 carriageway may be impacted during construction due to the presence of TM, plant, vehicles, machinery and operatives.

Mitigation

Throughout both phases the following mitigation measures will be implemented:

  • Works will be contained within the A77 carriageway extents.
  • Asset installation will be of a minimal visual impact (if any due to the like-for-like nature of the scheme) and will be in keeping with the current setting of the A77 carriageway within the scheme extents.
  • Visual screening will be used where possible to minimise visual impacts on surrounding receptors.
  • Where possible, vehicles, plant and machinery will be stored out of sight from nearby visual receptors. All site areas will be well-kept and tidy.

The residual effect on landscape and visual effects is deemed to be not significant. Therefore, in accordance with DMRB Guidance document LA 107: Landscape and Visual Effects no further assessment is required.

Biodiversity

Impacts

  • Increase in night-time noise may result in temporary disturbance/nuisance for nocturnal species if active in proximity.
  • There is no carriageway lighting throughout the scheme and any temporary lighting for the works may affect the foraging or commuting routes of nocturnal protected species which may be active in the surrounding area.
  • A Habitats Regulations Appraisal (HRA) was undertaken and has concluded that there will be no Likely Significant Effects (LSE) on the Glen App and Galloway Moors SPA due to the following:
  • The proposed works will not lead to a reduction of habitat area as the scheme works will be restricted to the existing carriageway only.
  • The proposed works are unlikely to lead to a disturbance given the ample alternative suitable habitat for the species within the surrounding area.
  • The proposed works will not lead to an increase in habitat or species fragmentation.
  • The proposed works will not lead to any loss of habitat / species.
  • The proposed works will not be located within the SPA. The proposed works will not cause any obstruction to the passage of any qualifying species. Birds may be temporarily disrupted by noise if passing close to the scheme. However, any temporary disruption has been assessed as negligible and mitigated by standard control measures.

Mitigation

The following mitigation measures will be in place for Phase 1 and Phase 2:

  • Operatives will remain vigilant for the presence of protected species within or near the works. If a protected species is seen on or near the scheme, all works will be stopped until the animal passes by. The protected species will not be approached, and the area will be temporarily isolated until the animal has moved on. Any sightings will be reported to the E&S Team.
  • Directional lighting will be used for all construction activities where works are required at night to minimise the impact of temporary lighting on foraging and commuting bats and other nocturnal species. This will include avoiding light spill onto watercourses and adjacent woodland parcels.
  • Impacts from noise will be kept to a minimum through the use of appropriate mufflers and silencers fitted to machinery. All exhaust silencers will be checked at regular intervals to ensure efficiency.
  • No vehicles, machinery or materials will be parked/stored on any soft verges.
  • Additional mitigation measures in Noise and Vibration and Road drainage and the water environment will be implemented.

It has been determined that the proposed scheme will not have direct or indirect significant effects to local Biodiversity.

Material assets and waste

Impacts

  • Both phases of works have the potential for resource completion through the use and transportation of primary material such as aggregates.
  • The design life for the TS2010 surfacing proposed is estimated to be 20 years. This will reduce the requirement for maintenance to this section of road over the period.
  • GHG emissions will be generated by material production and transporting to and from site.
  • Transportation and recovery of materials/waste will require energy deriving from fossil fuel, a non-renewable source.

Mitigation

Potential impacts related to pollution from materials and waste may result if these are not appropriately managed during construction. Therefore, the following regulatory requirements will be adhered to:

  • A SWMP will be prepared prior to the works which will detail how resource use and waste will be managed. This will help control and reduce the amount of waste produced, resulting in less landfilled waste.
  • The Contractor is responsible for the management and disposal of road planings arising from the works. All waste will be managed in accordance with the Environmental Authorisations (Scotland) Regulations 2025, under the relevant SEPA waste authorisation for recovery, reuse or disposal. For example, road planings will be prioritised for recovery or reuse, through recycling into new asphalt, in line with the waste hierarchy.
  • Waste will be transferred to SEPA-authorised facilities by carriers with valid waste carrier registration. A waste transfer note (WTN) will be completed for removal of waste from site and retained for two years, in line with statutory Duty of Care requirements.

The following mitigation measures will be implemented for Phase 1 and 2:

  • Materials will be derived from recycled, secondary or re-used origin as far as practicable within the design specifications to reduce natural resource depletion and associated emissions.
  • Any non-contaminated road planings arising from the works will be fully recycled in accordance with SEPA’s guidance on the Production for Fully Recovered Asphalt Road Planings.
  • Any coal tar-contaminated planings will be treated as special waste and taken off site for treatment/disposal at a licenced waste facility.

With best practice mitigation measures in place, the residual significance of effect on material assets and waste is considered to be not significant. Therefore, in accordance with DMRB Guidance document LA 110: Material Assets and Waste, no further assessment is required.

Noise and vibration

Impacts

  • TS2010 road surfacing which will be used for both phases is shown to have superior durability and noise reducing features compared to standard road surfacing mixes. Vehicle travellers and nearby local amenity users will benefit from improved road surfacing as a result of the scheme.
  • Noise heavy works will likely be required (temporarily) during nighttime hours, which could cause disturbance for nearby sensitive receptors (such as residential properties within 300m).

Mitigation

Mitigation measures follow Best Practicable Means as outlined in British Standard (BS) 5228:2009+A1:2014. The standard provides specific detail on suitable measures for noise control in respect to construction operations, for example:

  • Impacts from noise will be kept to a minimum through the use of appropriate mufflers and silencers fitted to machinery. All exhaust silencers will be checked at regular intervals to ensure efficiency.
  • Plant and machinery will be switched off when not in use to reduce noise disruptions to the surrounding environment.
  • Engine exhaust and vent silencers will be used where possible.
  • The noisiest works will be scheduled for before 11:00pm where feasible.
  • The delivery of materials to the scheme extents will be made during daytime and early evening hours where reasonably practicable, to reduce noise associated by traffic.
  • Operatives will avoid extraneous noise whilst onsite and will be briefed using the Amey Noise and Vibration environmental briefing.

The following further mitigation measures related to noise and vibration will be in place:

  • South Ayrshire Council Environmental Health Department has been notified of the works by the E&S Team, due to night-time programming.
  • Residential properties within 300m will be notified in advance of the works via letter drop, providing details of timings, nature, and duration of the works.

With best practice mitigation measures in place, and due to the works being of a minor, temporary, transient nature, no significant effects are predicted for noise and vibration. Therefore, in accordance with DMRB Guidance document LA 111: Noise and Vibration and no further assessment is required.

Population and human health

Impacts

  • Construction site lighting during night-time hours could cause disturbance for residential properties in close proximity, and for the nearby amenity users.
  • TM for the works will involve diversion routes and the re-routing of traffic. Nearby residents of surrounding settlements may experience travel disruption due to presence of TM, which may lead to increased journey lengths and times.
  • There will be no permanent or temporary impacts on land take from private land, community facilities or agricultural land as a result of the scheme as all works will be contained within the carriageway boundary.
  • Single access points to properties such as those in Smyrton and private land will be impacted by the scheme.
  • The core path at Smyrton will remain open during the works.

Mitigation

The following mitigation measures will be implemented for Phase 1 and 2:

  • TM will be advertised upon approach and in advance of the scheme. When in place, TM will be monitored to ensure it is effectively managing traffic flow.
  • Temporary site lighting used throughout the scheme will be directional and pointed only at the area of works.
  • Site specific control measures regarding noise and vibration, landscape and visual effects and air quality can be found in the relevant sections (above).
  • Due to night-time programming, properties within 300m of the scheme extents will be notified in advance of the works. Pre-notification will include details of proposed timings, duration of the works.
  • Single access points to properties and private land will be maintained at all times throughout the scheme.

With best practice mitigation measures in place, no significant effects on population and human health are predicted. Therefore, in accordance with DMRB Guidance document LA 112: Population and Human Health, no further assessment is required.

Road drainage and the water environment

Impacts

  • Potential for spills, leaks or seepage of fuels and oils associated with plant to escape and reach drainage systems if not controlled, which may impact the water environment.
  • If not appropriately controlled, debris and runoff from the works has the potential to enter nearby drains and watercourses and could detrimentally impact water quality.
  • In the event of a flooding incident, debris may be mobilised and could enter the road drainage having a detrimental effect on the surrounding local water environment.

Mitigation

The following mitigation measures will be implemented for Phase 1 and 2:

  • Best practice, as detailed by SEPA’s Guidance for Pollution Prevention (GPP5 and PPG6), will always be followed onsite. This will ensure that any potential debris/spills are not allowed to enter road drainage unchecked.
  • Appropriate measures will be implemented onsite to prevent any potential pollution to the natural water environment (e.g. debris, dust and hazardous substances). This will include, but will not be limited to, spill kits being present onsite at all times, and the use of funnels and drip trays when transferring fuel, and utilisation of drain covers/shielding boards.
  • Any pollution incidences will be reported to the Amey control room.
  • Operatives will conduct regular checks of the work site, especially in periods of heavy wind and rainfall.
  • All debris which has the potential to be suspended in surface water and wash into the local water environment will be cleaned from the site following the works.
  • Bunds will be provided around drums up to 205 litres with a buffer of 25% of their capacity, and around bulk storage to a capacity of 110% of the stored fuel/oil.
  • All plant and fuel storage at the site compound will be located on hardstanding and sited more than 10m from any watercourse.
  • All plant and fuel storage areas will be located away from areas that see high vehicular movement to prevent accidental damage.
  • All oils and fuels will be returned to storage area after use.
  • No refuelling will take place within 10m of any watercourse, including field drains and road drainage.
  • Weather reports will be monitored prior to and during all construction activities. In the event of adverse weather/flooding events, all activities will temporarily stop, and only reconvene when deemed safe to do so, and when run-off/drainage can be adequately controlled to prevent pollution.

Providing all works operate in accordance with current best practice, as demonstrated by SEPA’s GPPs the residual significance of effect on the water environment is considered to be neutral. Therefore, in accordance with DMRB Guidance document LA 113: Road drainage and the water environment no further assessment is required.

Climate

Impacts

  • GHG emissions will be emitted through the use of machinery, vehicles and materials used (containing recycled and virgin materials) and transporting to and from site.

Mitigation

The following mitigation measures will be implemented for Phase 1 and 2:

  • Local suppliers will be used as far as reasonably practicable to reduce travel time and GHG emitted as part of the works.
  • Vehicles/plant will not be left on when not in use to minimise and prevent unnecessary emissions.
  • Further actions and considerations for this scheme are detailed in the above Material assets and waste section.

With best practice mitigation measures in place, the residual significance of effect on climate is considered to be not significant. Guidance document LA 114: Climate, no further assessment is required.

Vulnerability of the project to risks

As the works will be limited to the resurfacing of the carriageway, there will be no change in vulnerability of the road to risk, or in severity of major accidents/disasters that would impact on the environment.

It has been determined that the proposed scheme will not alter the vulnerability of the existing trunk road infrastructure to risk of major accidents or disasters.

Assessment cumulative effects

The Scottish Road Works Commissioner's Interactive Map does not highlight any other works in the area at the time of construction.

South Ayrshire Council’s Planning Portal does not highlight any proposed developments or planning applications on the A77 carriageway within 2km of the scheme.

Amey’s current programme of works has not highlighted any other works on the A77 that will be undertaken in conjunction with the scheme.

No other nearby schemes which may result in a combined effect on nearby receptors have been identified.

Any future schemes will be programmed to take into account already programmed works, and as such any effect (such as from TM arrangements and potential construction noise) will be limited.